Task 4.2 : Produce and install the model turbine in the laboratory
The major objective of this project activity is to produce and install the model turbine in the laboratory.
The model turbine designed in WP 4.1 will be prepared for manufacturing. In this regard, the detail manufacturing drawing of the rig and the turbine will be prepared. While the turbines are being manufactured, the activities in WP 4.3 will be conducted in parallel. The final activity of this objective is to install the model turbine in the laboratory.
guide vane
Guide vane rig installed at TTL in KU during SEDIPASS Project. Photo: Sailesh Chitrakar
Deliverables 4.2
- Deliverables
D4.3 Manufacturing drawing of the rig/turbine - M16
D4.4 Model turbine at TTL for testing - M24
- Milestones
MS4.2 Model turbine procured in the lab for testing - M25