Elgesetergate 10 - When- Campus development
When
When
We are now finished with the refinement phase. We are now awaiting the startup grant from the Government.
The evaluation phase
15 September 2016: Tenders issued to five pre-qualified suppliers
23 January 2017: Tender deadline for design-and-build contract
April 2017: Contractor is chosen and final cost framework is submitted
Refinement phase
May 2017: Announcement of supplier for design-and-build contract
October 2017: Contract signed with supplier of design-and-build contract
November 2017: Start of refinement phase
October 2017: Funding from the National Budget clarified
March 2018: Solutions have been processed
May 2018: Statsbygg sends their report on phase process of the feasability study to Backe
June 2018: Statsbygg sends the feasability study to the Ministry of Education and Research
The construction phase
2019: Expected construction start
2022: Expected completion